Upgrade existing HV supply and install new HV ring feed (backup) supply for new Maximum Security Site. Install two new 1500kVA kiosk transformers. Reconductor existing network.
Project: Junee Jail
Builder: CPB Construction
Time Frame: 4 Months
Scope of Electrical and Communications Services Works:
- Remove existing 2 x 750kVA kiosk transformers and HV incoming switch
- Reconductor 1.5km of overhead HV 3 phase existing powerline
- Install 1500m of new HV UG cable, 2 x new 1500kVA kiosk transformers, 23 x HV pole top hardware upgrade, 13 x HV pole replacement, 1 x new HV pole top gas switch,
- Upgrade overhead pole top Transformer from 25kVA to 200kVA for increased load.