RAAF Base – Sub 8 and 2A upgrade – Wagga Wagga

Supply upgrade of 2 substation sites at the RAAF Defence Base in Wagga Wagga.



Project:
RAAF Base – Sub 8 and 2A upgrade – Wagga Wagga
Builder: Defence/ Spotless
Time Frame: 2 Months

Scope of Electrical and Communications Services Works:

  • New 1000kVA NHP supplied & installed to replace existing 750kVA TX at sub 8.
  • The existing 750kVA TX from sub 8 was then relocated to upgrade the existing 500kVA in sub 2A