Supply upgrade of 2 substation sites at the RAAF Defence Base in Wagga Wagga.
Project: RAAF Base – Sub 8 and 2A upgrade – Wagga Wagga
Builder: Defence/ Spotless
Time Frame: 2 Months
Scope of Electrical and Communications Services Works:
- New 1000kVA NHP supplied & installed to replace existing 750kVA TX at sub 8.
- The existing 750kVA TX from sub 8 was then relocated to upgrade the existing 500kVA in sub 2A